Description of Project:

 

Recent EU support to Kiribati under the 9th European Development Fund – Improvement of Outer Island Health Services Project - included the planning and construction of dispensaries and health centres distributed throughout the Outer Gilbert Islands to enhance access to medical and health services for their local communities.


Between August 2007 and November 2009 there were 18 health centres and 56 dispensaries built to a standard design which included solar power supply and water storage tanks, however, at the final audit of the project in 2013, insufficient evidence relating to a large proportion of reported expenditure was encountered.


The purpose of the mission is to verify the cost of the infrastructure component of the project. Firstly to corroborate that the reported works were carried out as planned, secondly to establish an itemised cost basis for the completed works which can be used by the EU Delegation to decide on amounts certifiable.


Summing up, the global objectives of this technical evaluation are to:


1. Provide an overall project cost for the infrastructure-related components (inclusive of material, labour, mobilisation and any other related costs)


2. Quantify the materials used for the particular project and provide an estimated cost of the quantified materials

Services Provided:

 

  • Evaluate whether the works have been carried out as shown in the plans and that these have been carried out in the locations indicated.
  • Determine the bill of quantities of the buildings from the as built drawings
  • Carry out a cost estimate of the labour and materials used for the construction of all the buildings
  • Carry out a detailed survey of the solar photovoltaic systems installed on the health centers/dispensaries and quantify the materials (solar panels, charge controllers, inverters, batteries, wiring and accessories) used.
  • Carry out a cost estimation of the labour and materials used for the installation of the solar panels on all the buildings
  • Carry out a detailed survey of the water reticulation system installed in these health centers/dispensaries and quantify the materials (water tanks, stands, pumps, reticulation piping and accessories) used.
  • Carry out a cost estimation of the labour and materials used for the installation of the water reticulation system in all the buildings
  • Determine the logistical costs of transportation of material from source to the project sites via Tarawa.
  • Determine the storage costs of the materials in Tarawa and the project sites if any.
  • Determine where necessary any cost incurred in the site works prior to the construction of the buildings
  • Outline and determine any other related costs to the project
  • Provide an estimated total cost of the project, considering the various costs (buildings - material & labour-, energy supply and water reticulation system, including site works and mobilisation to the various sites).

Name of Partners:

 

  • Planet SA-Greece (Leader)